jcth
Civil/Environmental
- Aug 13, 2018
- 3
Greetings; I install (typically) temporary water remediation systems.
Scenario:
12 qty - 21k temporary holding tanks (Baker Tanks; Frac Tanks, etc…);
6” mid-low tank outlet ports feed (via hose or pvc pipe) a common 6” pvc manifold about 80’ long in front of tanks providing pump inlet suction supply.
Two or three centrifugal pumps with flooded suction from tank inlet supply manifold, discharge/pump down tanks at 1800 gpm total output required. Pumping Medium is water at ambient temp (50F).
Best practices: 5-10 pipe i.d. straight inlet run to pump suctions; 1-2 suction Dia sizes larger than pump suction Dia; suction velocity no higher than 8 ft/sec.
Question a) do I consider overall velocity in the 6” tank manifold inlet supply? Or just in the straight run suction inlet to pump?
If I just consider individual pump suction velocities splitting flows then:
b) two pumps at 900 gpm each is over 10 ft/sec suction velocity and problematic?
c) three pumps at 600 gpm each is under 7 ft/sec suction velocity and better?
Why - justifying increased costs of suction plumbing sizes SOP’s, freeing up pump fleet over utilization, and reducing pump wear and tear…
Thank you for feedback and guidance.
Scenario:
12 qty - 21k temporary holding tanks (Baker Tanks; Frac Tanks, etc…);
6” mid-low tank outlet ports feed (via hose or pvc pipe) a common 6” pvc manifold about 80’ long in front of tanks providing pump inlet suction supply.
Two or three centrifugal pumps with flooded suction from tank inlet supply manifold, discharge/pump down tanks at 1800 gpm total output required. Pumping Medium is water at ambient temp (50F).
Best practices: 5-10 pipe i.d. straight inlet run to pump suctions; 1-2 suction Dia sizes larger than pump suction Dia; suction velocity no higher than 8 ft/sec.
Question a) do I consider overall velocity in the 6” tank manifold inlet supply? Or just in the straight run suction inlet to pump?
If I just consider individual pump suction velocities splitting flows then:
b) two pumps at 900 gpm each is over 10 ft/sec suction velocity and problematic?
c) three pumps at 600 gpm each is under 7 ft/sec suction velocity and better?
Why - justifying increased costs of suction plumbing sizes SOP’s, freeing up pump fleet over utilization, and reducing pump wear and tear…
Thank you for feedback and guidance.