Jfk1
Aerospace
- Jun 4, 2001
- 12
We have a humidity problem on a 220 Ton CW system. The Chillers were recently replaced and new circulating pumps were added. The circulating pumps have a rating each of 375 GPM and TDH of 110 Ft.
The return water has only a 6-7 F rise from the supply temperature
I understand there is a rule of thumb of 3 GPM per Ton of cooling and that Trane has used 2 GPM per Ton of cooling. Are short on GPM for our system?
The return water has only a 6-7 F rise from the supply temperature
I understand there is a rule of thumb of 3 GPM per Ton of cooling and that Trane has used 2 GPM per Ton of cooling. Are short on GPM for our system?