Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Clear Span as specified in SDI

Status
Not open for further replies.

sb79

Structural
Apr 29, 2013
12
When it says clear span on SDI (Steel Deck Institute), does it mean from center line (web to web) or flange tip to flange tip.

Thanks in advance.

 
Replies continue below

Recommended for you

We use centerline of support for beams and joists - the location of the flange tips vary so much in our projects and the slight difference in capacity isn't worth the effort to calculate.

 
I agree with JAE. You also have sweep in steel beam, along with erection tolerance, and the CL distances should be enough to counteract those issues.
 
Thank you JAE and structSU10

But in my project there are only three of them, so my question again will be if we can calculate the length from flange tip to flange tip then can I use that as clear span or I still have to use from center line of web to web as clear span
 
What does it matter if your capacity is 166 psf for clear span and 162 psf for center-to-center, if your applied load is only 100 psf.
 
One simple question, zero answers to that simple question. Clear span means from flange tip to flange tip.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor