Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations cowski on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

CMU walls- NO hook into bond beam

Status
Not open for further replies.

ChiefInspectorJ

Specifier/Regulator
May 28, 2015
40
While doing threshold inspections I have noticed the absence of vertical to horizontal 8" rebar hooks into the bond beam. The vertical rebar is 6" vertical into the bond beam? I assume the rebar functions as a anchor bolt but it is not spliced to the horizontal bond beam rebar. The CMU walls were 22" high and in 140 mph wind zone.
What is the difference in uplift capacity between the 2 methods?
 
Replies continue below

Recommended for you

Do you know how far they are embedded into the bond beam? It’s not ideal but if the bars extend to the top of the bond beam you would think they would develop enough strength to exceed the capacity of whatever is connecting to it applying the uplift loads, unless your uplift is really high. How deep is the bond beam and what’s framing to it?
 
Is the bond beam at the top of the wall? and, is the vertical reinforcing really required? if not, then no need for development.

Dik
 
It is an 8" CMU bond beam.Trusses or bar joist span 60'. Rebar is 48" oc. Truss anchorage does not always line up with the rebar. So I assume the bond beam and lintels are held down by the 6" embedment into the bond beam.I have seen these CMU bond meams ripped off the top of house walls by 100 mph winds.
 
Then you need better anchorage... a roof membrane had blown of a water treatment building in Lindsay, Ontario twice before they secured it to the top of the masonry wall... next time it blew off, it took of the top course of block...

Dik
 
Ask the SE if there are net wind uplifts along the wall....per code wind there may not be any.

Check out Eng-Tips Forum's Policies here:
faq731-376
 
A single high bond beam might not be deep enough to develop a hook or, said another way, a hook might not provide any additional capacity over the 6" straight embedment.

 
JLNJ: it should... don't know how much, but, it is an improvement.

As JAE pointed out... is there any uplift on the roof connection... if not, then anchorage is not an issue. It is, however, nice to have...

Dik
 
Unless you have concrete on the roof there’s going to be a good amount of uplift. If so, the whole system seems a little suspect if you ask me. 60’ joists anchoring into an 8” bond beam and a 22’ wall with rebar at 48” doesn’t sound like it’s engineered for 140 mph. If you wanted to tie the bond beam down a little better you could use some Simpson light gauge straps with 1/4” concrete screws that extend from the bond beam down a few courses to help develop the rebar.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor