Typically I have used the value of 0.1 but have been told in the past that taking 0.5 is more realistic and that 0.1 is on the conservative side. The detail would be checking sliding in a small residential building with the dpc between the underside of the ground floor slab and the masonry underbuild.
What value do other members usually take for this? I cannot find anything online which suggests a value.