Elindio1
Structural
- Oct 13, 2006
- 21
I'm verifiyng if it is possible to install a cold storage room inside an existing warehouse over an existing 6" slab. The room is to operate at 2 C / 35.6 F. The cold room provided says that no demolition of the slab is required but I think there is going to be some heaving or swelling in the slab so I will need to install some type of heating system to the slab. Is there a "treshhold" temperature below which heaving will occur (0 C)? Or in this case the temperature is not that low so no heaving could be expected?
Thanks!
Thanks!