We are putting up a 4 story building, simple framing. W8x67 is the largest col member size. Some of the piers are 1"1/2 too low. Can the columns be shimmed to compensate for this elevation change?
If we can shim up to 1"1/2 should the shims be comb type and welded together so as not to slip?
If we can shim up to 1"1/2 should the shims be comb type and welded together so as not to slip?