petertor
Specifier/Regulator
- Jun 8, 2004
- 15
We have a D-B contract with a large multinational consultant and process equipment vendor.
We have to provide the foundation design for their process equipment on the barge already.
We asked them for environmental load data they used, equipment loads and anchorage results,
you know, just to make sure they did all the 7-10 load combinations for wind and seismic.
They are demanding an additional fee to develop that information for our foundation design.
And because they're a large multinational, they want an OPEN END P.O. to develop the loads.
Is that normal? In 30 years I've never had a vendor demand more money for anchorage loads.
This is a package process unit, all the consultant is doing is pipe runs and connections.
The vendor should have this pre-calc'd. Vendors give the loads, we design the foundations.
Or did Earth pass thru an alternate dimension after the last solar X-burst, and I'm wrong? ; )
We have to provide the foundation design for their process equipment on the barge already.
We asked them for environmental load data they used, equipment loads and anchorage results,
you know, just to make sure they did all the 7-10 load combinations for wind and seismic.
They are demanding an additional fee to develop that information for our foundation design.
And because they're a large multinational, they want an OPEN END P.O. to develop the loads.
Is that normal? In 30 years I've never had a vendor demand more money for anchorage loads.
This is a package process unit, all the consultant is doing is pipe runs and connections.
The vendor should have this pre-calc'd. Vendors give the loads, we design the foundations.
Or did Earth pass thru an alternate dimension after the last solar X-burst, and I'm wrong? ; )