MHSpurs
Structural
- Apr 11, 2005
- 29
We are investigating the bond of a thin high strength concrete screed 2" to existing concrete floor using an SBR. Prep includes saturating the floor and grit balsting to expose aggregate.
using pull off testing, can anyone tell me what bond strengths should be achieved?
Also, at what strength would concrete (original slab) failure be expected? The original slab is 35N, 10 years old and in relatively good condition.
Thanks
MH
using pull off testing, can anyone tell me what bond strengths should be achieved?
Also, at what strength would concrete (original slab) failure be expected? The original slab is 35N, 10 years old and in relatively good condition.
Thanks
MH