Ingenuity
Structural
- May 17, 2001
- 2,348
A lively discussion on a job site recently.
Construction of a carpark ramp between a ground floor (recently constructed slab on grade) and an upper parking level (recently constructed with PT).
Ramp is RC slab and beam at a slope of 16% (approx 9 deg). Length of ramp is about 20m (66').
There is NOT fully continuous reinforcement in the top of slab - only mesh/fabric over the intermediate RC support beams.
Line pump concrete mix is 80mm (3") slump and 32MPa (4500 psi).
Question: Do you start placement of concrete from bottom of ramp or top of ramp?
Assuming that cost of a line pump vs boom pump hire is approx the same.
Interested in your opinion.
Construction of a carpark ramp between a ground floor (recently constructed slab on grade) and an upper parking level (recently constructed with PT).
Ramp is RC slab and beam at a slope of 16% (approx 9 deg). Length of ramp is about 20m (66').
There is NOT fully continuous reinforcement in the top of slab - only mesh/fabric over the intermediate RC support beams.
Line pump concrete mix is 80mm (3") slump and 32MPa (4500 psi).
Question: Do you start placement of concrete from bottom of ramp or top of ramp?
Assuming that cost of a line pump vs boom pump hire is approx the same.
Interested in your opinion.