bookowski
Structural
- Aug 29, 2010
- 983
When pouring a concrete wall(s) the worst case design pressure would be p = (w x h). If the wall is poured in lifts or at a slow rate then the concrete should be setting up and reduce that pressure, i.e. reduce the effective 'h'. The time required would vary by the particular mix, but are there any guidelines out there for this? ACI 347 notes 'for forms that can be filled rapidly before stiffening of the concrete takes place, h should be taken as the full height of the form'.
What would be a reasonable way to determine how long is required, or what pour rate, to not need the full 'h'?
(Assume that I can't provide ties to take the full w x h)
What would be a reasonable way to determine how long is required, or what pour rate, to not need the full 'h'?
(Assume that I can't provide ties to take the full w x h)