I want to do a Continuous beam with 15 spans each span 5 meters.
It cannot be complete in one shot, so I have to divide the pouring in two parts.
First part 7 spans and second part with 8 spans.
For the first part, where should I stop?
should I stopped at column Number 7, or 1 m away from the column?
any advise please?
It cannot be complete in one shot, so I have to divide the pouring in two parts.
First part 7 spans and second part with 8 spans.
For the first part, where should I stop?
should I stopped at column Number 7, or 1 m away from the column?
any advise please?