remark
Structural
- Jun 14, 2007
- 2
I have a recently constructed composite slab on metal deck /steel beam floor system that the contractor has sawcut in 1 1/4" control joints. This comprimises the gravity capacity of the floor system.
Is there a method in which to treat the control joint to re-establish the contrete section or possibly a retrofit to the beams/stud confirguration to increase its capacity?
Is there a method in which to treat the control joint to re-establish the contrete section or possibly a retrofit to the beams/stud confirguration to increase its capacity?