Guest
Hi all.
I'm having trouble setting up my project plan the same way as a friend of mine has theirs.
We have the same Calendar settings, but her durations are calculating differently than mine.
For example. Her start date is the 8th, end is the 9th. Her duration is 1 day.
My start date is the 8th, end is the 9th. My duration is 1.88 days. Why isn't it 1 day or 2 days? And if it should be two days, why is my MS project different than my friends?
Thanks in advance for your help
I'm having trouble setting up my project plan the same way as a friend of mine has theirs.
We have the same Calendar settings, but her durations are calculating differently than mine.
For example. Her start date is the 8th, end is the 9th. Her duration is 1 day.
My start date is the 8th, end is the 9th. My duration is 1.88 days. Why isn't it 1 day or 2 days? And if it should be two days, why is my MS project different than my friends?
Thanks in advance for your help