mish
Civil/Environmental
- Jul 28, 2003
- 1
I have written a detailed construction schedule into MS Project 2000. Now I want to display and print programs/schedules showing only the tasks relevant to the various component suppliers. Ideally just by manually selecting the required tasks. Task Filtering does not appear to let me do this. I tried assigning a material resource to one set of tasks I want to separate out, but couldn't get this to help me either. Surely it's not unusual to want to communicate subsets of the whole program to various suppliers? Am I missing something very simple?