I am assigned to design a spill way for LNG tank. It is to drain LNG in case flange failure. While sizing the vertical drain piping, I was told to use self-venting design which limites froude # <0.3.
My questions are:
1. If design for full flow(froude # =0.8), is it acceptable? what bad will happen?
2. Is that necessary to design for self venting for this never or once in the tank lifetime scenario? The reason is the cost difference betw 12" and 20" SS pipe.
Thank in advance.
My questions are:
1. If design for full flow(froude # =0.8), is it acceptable? what bad will happen?
2. Is that necessary to design for self venting for this never or once in the tank lifetime scenario? The reason is the cost difference betw 12" and 20" SS pipe.