EEJaime
Electrical
- Jan 14, 2004
- 536
Gentlemen,
I have recieved different answers to this question from our Structural fellows in this company. Thought I would take advantage of the expertise here.
I have a concrete encased electrical conduit bank consisting of 40+ 4" diameter conduit entering a building from below grade on site into a basement level electrical room. The facility is an important facility, in a seismic zone 4 in California. The basement wall is a reinforced concrete wall which at our entry point is 24" thick. I have detailed the conduit to enter through a series of 6" diameter sleeved openings utilizing the "Link-Seal" assembly system with 6" between sleeves vertically and horizontally. The conduit that passes through the wall is a 10' length of rigid galvanized steel conduit. Inside the building it transitions to EMT, outside to PVC.
My question is: At the concrete encasement of the conduit bank approaches the basement wall- can it be poured directly against the wall? Or do I need a gap of a few inches between the basement wall and the beginning of the conduit encasement?
Normally there is no seismic joint gap required below grade, but in this case only half of the installation is below grade. The basement finished floor elevation is +0'-0", the conduit enter about 16' above that.
Any comments would be apprecieated.
Sincerely
EEJaime
I have recieved different answers to this question from our Structural fellows in this company. Thought I would take advantage of the expertise here.
I have a concrete encased electrical conduit bank consisting of 40+ 4" diameter conduit entering a building from below grade on site into a basement level electrical room. The facility is an important facility, in a seismic zone 4 in California. The basement wall is a reinforced concrete wall which at our entry point is 24" thick. I have detailed the conduit to enter through a series of 6" diameter sleeved openings utilizing the "Link-Seal" assembly system with 6" between sleeves vertically and horizontally. The conduit that passes through the wall is a 10' length of rigid galvanized steel conduit. Inside the building it transitions to EMT, outside to PVC.
My question is: At the concrete encasement of the conduit bank approaches the basement wall- can it be poured directly against the wall? Or do I need a gap of a few inches between the basement wall and the beginning of the conduit encasement?
Normally there is no seismic joint gap required below grade, but in this case only half of the installation is below grade. The basement finished floor elevation is +0'-0", the conduit enter about 16' above that.
Any comments would be apprecieated.
Sincerely
EEJaime