Has anyone enlarged an existing concrete spread footing by doweling reinforcing into the sides and pouring a larger footing around the 4 edges of the existing? (adding floors to existing building)
Not my idea, I would like to remove the existing and build a new footing. The builder suggested this to save shoring costs and minimize disruption to on-going operation at the footing level.
The Owner of course thought this was a wonderful idea!
I'm cross posting to geotech also.