spieng89
Structural
- Jun 30, 2015
- 172
I have an existing spread footing I am adding on to and placing a pier above. Field observations have shown that, contrary to the original design drawings, the edge of the existing footing is inline with the epoxy anchor placement.
My question is, is it okay to proceed with epoxy install at this cold joint or would it be better practice to chip the existing foundation back a few inches and epoxy into the new footing expansion? The anchor rod location can not be moved due to project constraints. Attached a sketch
My question is, is it okay to proceed with epoxy install at this cold joint or would it be better practice to chip the existing foundation back a few inches and epoxy into the new footing expansion? The anchor rod location can not be moved due to project constraints. Attached a sketch