I work in the fairly specialized field of concrete formwork and shoring.
With the down turn of the economy, a number of projects in my working area have stalled, stopped, had their initial contracts terminated and have come up for subsequent rebid.
On one such project, the structure was 75% complete at the time of shutdown and shoring and formwork were left installed, waiting for concrete placement.
My company was not initially involved with this project, but we wre asked to come out and complete a bid for continuing the work.
In the process of reviewing the in place work, the details used to install the temporary work was shared with us and upon review, I found the system to be installed in the wrong principle direction and the materials used to be of a lower grade than that specified in the stamped details.
While the pricing of my company included the cost of having me redesign the in place system to carry the applied loads through supplemental shoring, a number of our competitors do not maintain in house engineering and use the same consultant for design that originally provided the shoring details which are not installed correctly.
Regardless, I feel some sense of obligation to notify the EOR of the temporary works of the issue or notify the EOR of the structure.
Am I off base or does anyone have any thoughts or recommendations to share?
I do appreciate any advice you may offer.
Daniel
With the down turn of the economy, a number of projects in my working area have stalled, stopped, had their initial contracts terminated and have come up for subsequent rebid.
On one such project, the structure was 75% complete at the time of shutdown and shoring and formwork were left installed, waiting for concrete placement.
My company was not initially involved with this project, but we wre asked to come out and complete a bid for continuing the work.
In the process of reviewing the in place work, the details used to install the temporary work was shared with us and upon review, I found the system to be installed in the wrong principle direction and the materials used to be of a lower grade than that specified in the stamped details.
While the pricing of my company included the cost of having me redesign the in place system to carry the applied loads through supplemental shoring, a number of our competitors do not maintain in house engineering and use the same consultant for design that originally provided the shoring details which are not installed correctly.
Regardless, I feel some sense of obligation to notify the EOR of the temporary works of the issue or notify the EOR of the structure.
Am I off base or does anyone have any thoughts or recommendations to share?
I do appreciate any advice you may offer.
Daniel