Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Existing pipe below new slab on grade

Status
Not open for further replies.

WWTEng

Structural
Nov 2, 2011
391
Situation: Exist 8" water main, not in use anymore, invert level 5' below top of new proposed 5" SOG. The contractor is wondering if he can fill the pipe with concrete, cap it each end and leave it in place.

Personally I think at the given depth it should be OK. Concrete in the pipe will shrink a little but due to the depth of the pipe, any pressure from the slab can bridge around the pipe.

 
Replies continue below

Recommended for you

Probably doesn't need to be grouted, but grouting won't hurt. What is the alternative? Digging a trench to take the pipe out just creates another excavated and filled area which could create more problems than leaving the pipe in place.
 
I can't believe that the load from a 5" sog would crack an 8" water main 5 feet down, used or not. Seems like a lot of room for the load to the slab to spread out and dissipate. Save your money and move on.

Mike McCann
MMC Engineering
 
Probably depends more on the overdig for the pipe than the pipe itself
 
What are the design loads on the SOG? What is material is the water main made from? Soil type?
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor