omsava
Chemical
- Jun 16, 2006
- 2
This is my first time at doing such an audit to ensure adequate orifice area per a HazOp study recommendation. This PSV is on a fractionator originally designed as a deethanizer but is now being used as a depropanizer. The feed to the column is mostly butanes with some propane. It is operated on total reflux and overhead propane ends up in our fuel system while the bottom butanes in LPG. The PSV is set at 550 psig per its original function.
1. In a fire scenario, assuming 100% n-butane the relief conditions become very close to its critical poperties ~ 565 psig and 305 F.
2. Ignoring the above and performing the calculations per Consolidated's API Fire Sizing for liquid hydracarbons the required orifice area is less than the actual.
How should I proceed from here to determine the adequacy of the PSV?
Thanks.
1. In a fire scenario, assuming 100% n-butane the relief conditions become very close to its critical poperties ~ 565 psig and 305 F.
2. Ignoring the above and performing the calculations per Consolidated's API Fire Sizing for liquid hydracarbons the required orifice area is less than the actual.
How should I proceed from here to determine the adequacy of the PSV?
Thanks.