KayneR
Structural
- Jul 10, 2017
- 6
Hi there,
So the reason I have this question is that we had to design a prop to support a tilt panel wall before it was tied into the steel portal structure.
we can size the prop and tie it into the tilt panel easy enough. We can analyse the shear for where the prop is tied into the existing concrete slab.
Where we are struggling is for the uplift component at the existing slab.
We can size what the expected uplift will be and we put the appropriate factors of safety on this. But what area of concrete can we assume to pick up beyond the fixing?
The strengths of the fixings might say 25kN, we have a 100mm slab of concrete, to pick up 25kN we would need an area of 10.4 m^2. This seems like a lot. The slab is reinforced with a high strength mesh.
The fixing manufacturers fix their products into concrete and then have supports either side so that there will always be enough resistance, may not be totally applicable.
Does anyone have rule of thumb or know where to find something that says how far beyond a fixing you can pick up load?
Note the values I have used are arbitrary, I am more looking for a better understanding of a principal rather than a solution.
So the reason I have this question is that we had to design a prop to support a tilt panel wall before it was tied into the steel portal structure.
we can size the prop and tie it into the tilt panel easy enough. We can analyse the shear for where the prop is tied into the existing concrete slab.
Where we are struggling is for the uplift component at the existing slab.
We can size what the expected uplift will be and we put the appropriate factors of safety on this. But what area of concrete can we assume to pick up beyond the fixing?
The strengths of the fixings might say 25kN, we have a 100mm slab of concrete, to pick up 25kN we would need an area of 10.4 m^2. This seems like a lot. The slab is reinforced with a high strength mesh.
The fixing manufacturers fix their products into concrete and then have supports either side so that there will always be enough resistance, may not be totally applicable.
Does anyone have rule of thumb or know where to find something that says how far beyond a fixing you can pick up load?
Note the values I have used are arbitrary, I am more looking for a better understanding of a principal rather than a solution.