eegultekin
Civil/Environmental
- Sep 18, 2014
- 8
hi. i am designing two floor steel factory. At mezanine floor using composite beam with 8 cm concrete. And planing to put energy panels at roof. i have several questions.
1. Roof has a %2 slope. starts with 7.5 meters and finishes at 8.00 meter. How can we use rigid diaphragm? ETABS warning is you cant create rigid diaphragm at different levels.
2. Can we use foamed-concrete over metal-deck? In turkey there is foamed concrete with 1 MPa strength and 400kg/m3 density. I think it is strength enough to make a rigid diaphragm. I am wondering is there any construction abroad using this material over metal-deck. I searched from internet, generally there is lightweight concrete with 1600 kg/m3 density and high strength.
1. Roof has a %2 slope. starts with 7.5 meters and finishes at 8.00 meter. How can we use rigid diaphragm? ETABS warning is you cant create rigid diaphragm at different levels.
2. Can we use foamed-concrete over metal-deck? In turkey there is foamed concrete with 1 MPa strength and 400kg/m3 density. I think it is strength enough to make a rigid diaphragm. I am wondering is there any construction abroad using this material over metal-deck. I searched from internet, generally there is lightweight concrete with 1600 kg/m3 density and high strength.