Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Footing Dowel Design - Transfer of Moment/Tension

Status
Not open for further replies.

EngrJS1

Civil/Environmental
May 1, 2022
19
Hi,

A moment which induces tension is needed to be transferred to my footing. How do I determine the required dowel area to transfer this moment/tension?
 
Replies continue below

Recommended for you

OP, have you designed the reinforcement in the column that will transfer the forces to the footing? If so, then you know how to determine the required dowel area! Make sure to take care in detailing that connection, looking for details such as maximum steel in the column and development. Assuming your firm has typical details for footings, review those and that should give you a hint for what this would look like.
 
EngrJSI said:
A moment which induces tension is needed to be transferred to my footing. How do I determine the required dowel area to transfer this moment/tension?

Turn the thing upside down in your head and you'll see that it's the same situation as the connection between a roof slab and column. As such, you need to tend to many of the same issues:

1) Eccentric punching shear in the the footing.

2) Rebar detailing that is able to redirect tension around the corner of the joint.

3) Quite possibly, top steel in your footing in addition to bottom steel.

Quite often one is pressured to allow the footing dowels to be turned outwards rather than inwards for constructability reasons. That is quite often allowed despite being a bit dubious technically.

C01_b9f4ck.png
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor