ChemEngSquirrel
Chemical
- Jun 10, 2010
- 72
I have a demethanizer column and im sizing the psv for the blocked vapor outlet case.
Ive simulated the scenario in hysys with max reboiler duty allowed for in the model.
Is steady state simulation the correct approach for this scenario?
Thanks.
Ive simulated the scenario in hysys with max reboiler duty allowed for in the model.
Is steady state simulation the correct approach for this scenario?
Thanks.