bouk715
Structural
- Apr 24, 2005
- 59
I'm hoping that someone here will be able to shed some light on this topic...
We have a project currently in construction here in the northeast. Like most of the country, we've had some very cold temperatures the last few days. The contractor placed a concrete foundation wall early last week (roughly 10"-12" thick). The wall was covered with insulated blankets after placement. The ambient temperature dropped well below freezing shortly after placement (within 24-36 hours). Test cylinders were cast and a couple were left at the site for field curing to determine strength gain during cold temperatures to determine acceptable form removal and backfilling time-frames (the project specs had timeframes, but the contractor wanted to see if he could hasten it by reaching strengths earlier). According the testing agency, the cylinders were kept under the blankets.
A cylinder was picked up from the site to check 4-day compressive strength, and it was determined that the sample was frozen. So what I'm not sure about is if the wall itself froze or if it was just the sample. I assume since the sample is so small compared to the larger wall, they wouldn't freeze at nearly the same rate. The testing agency came back the next day (after 4 day break) and did 3 windsor probe tests. Results came back between 2,300 psi and 5,000 psi. Mix design is 4,000 psi at 28 days. The testing agency will be back again to take 3 concrete core tests after the concrete has been in place at least 14 days to test the compressive strength and confirm the windsor test results.
My question is, assuming the core compression tests come back okay (say at least 7-day strength), should I request any other tests on the wall? Could there be voids in the concrete if it partially froze, even if it looks okay from the exterior and compression tests come back acceptable? Is petrographic the only reliable test to check for the voids?
Any comments would be greatly appreciated. Thanks.
We have a project currently in construction here in the northeast. Like most of the country, we've had some very cold temperatures the last few days. The contractor placed a concrete foundation wall early last week (roughly 10"-12" thick). The wall was covered with insulated blankets after placement. The ambient temperature dropped well below freezing shortly after placement (within 24-36 hours). Test cylinders were cast and a couple were left at the site for field curing to determine strength gain during cold temperatures to determine acceptable form removal and backfilling time-frames (the project specs had timeframes, but the contractor wanted to see if he could hasten it by reaching strengths earlier). According the testing agency, the cylinders were kept under the blankets.
A cylinder was picked up from the site to check 4-day compressive strength, and it was determined that the sample was frozen. So what I'm not sure about is if the wall itself froze or if it was just the sample. I assume since the sample is so small compared to the larger wall, they wouldn't freeze at nearly the same rate. The testing agency came back the next day (after 4 day break) and did 3 windsor probe tests. Results came back between 2,300 psi and 5,000 psi. Mix design is 4,000 psi at 28 days. The testing agency will be back again to take 3 concrete core tests after the concrete has been in place at least 14 days to test the compressive strength and confirm the windsor test results.
My question is, assuming the core compression tests come back okay (say at least 7-day strength), should I request any other tests on the wall? Could there be voids in the concrete if it partially froze, even if it looks okay from the exterior and compression tests come back acceptable? Is petrographic the only reliable test to check for the voids?
Any comments would be greatly appreciated. Thanks.