With another cladding fire in Daubi - lets take a look at the progress in the Grenfell Tower Inquiry

As the Grenfell Tower Inquiry prepares to return for closing statements, Peter Apps recaps some of the evidence relating to the testing, sale and certification of materials used in the building’s cladding system
Grenfell Tower Inquiry recap: module two – the cladding; INSIGHT 01.11.22 7.00 AM BY PETER APPS

At the bottom of this article, there is a summary by week of each of the 84 weeks of testimony so far.

Will the cost ever reach a point where the ACM panel hazard is removed from buildings?
 
Replies continue below

Recommended for you

The Grenfell Tower Disaster 2017 | Plainly Difficult Documentary: Plainly Difficult posted Dec 3, 2022.

Grenfell Tower Inquiry, Link to inquiry site

to recap
The Inquiry is investigating a List of Issues that has been separated into two phases. Phase 1 focuses on the factual narrative of the events on the night of 14 June 2017. Hearings for Phase 1 began on 21 May 2018 and concluded on 12 December 2018. The Chairman published his Phase 1 report on 30 October 2019, the contents of which can be found here.

Phase 2 of the Inquiry examines the causes of these events, including how Grenfell Tower came to be in a condition which allowed the fire to spread in the way identified by Phase 1. 

Phase 2 Overarching and Module 7 Closing Statements - Thursday 10th November 2022
Link to part 1
Link to part 2

More hearing videos

Phase 2 report pending.