We are in a 1920's NYC building where our floor is intact but the ceiling below is starting to spall off the wire reinforcement and there is some partial corrosion to full failure of the wire. There is no rebar, the structural slab concrete is cinder concrete (I am told approx. 700 psi) and is approximately 5" thick. Then there is a non-structural cinder concrete top slab that is about another 4" thick. On top of that is modern waterproofing with a tile floor. There is no water entering the slab at this time. The spalling damage is due to historic water damage and carbonization and has been exacerbated by time and the continued corrosion of the wire.
We have to do the repair essentially 100% from below.
We want to do a grillage type repair from below, with 2-1/2" galvanized decking supported by 4" "railroad" beams that are tied to the structural steel.
The repair is somewhat complicated by the fact that the floor structural steel is laid out with diagnol bracing in each bay.
Is there a "standard procedure" for filling concrete or grout between the decking and the existing slab above?
Thanks for any answers!
We have to do the repair essentially 100% from below.
We want to do a grillage type repair from below, with 2-1/2" galvanized decking supported by 4" "railroad" beams that are tied to the structural steel.
The repair is somewhat complicated by the fact that the floor structural steel is laid out with diagnol bracing in each bay.
Is there a "standard procedure" for filling concrete or grout between the decking and the existing slab above?
Thanks for any answers!