I was hoping I could get some help here. I run into a hand sketch exercise that I would like to compare. Here is the problem:
Design a system with an inlet, discharge, and a method for monitoring pressure. Our client will install the system inline between their pump and injection point, which are approximately 20 meters apart within the same building.
Some design criteria has already been established:
¾” Swagelok tube/fittings, flanged inlet/outlet
Design of 600 psi, ambient
304 s.s. frame to be mounted on the wall
Pressure guage with isolation seal and valve
1. Provide a hand sketch P&ID
2. Provide a hand sketch GA
Thank you.
I was hoping I could get some help here. I run into a hand sketch exercise that I would like to compare. Here is the problem:
Design a system with an inlet, discharge, and a method for monitoring pressure. Our client will install the system inline between their pump and injection point, which are approximately 20 meters apart within the same building.
Some design criteria has already been established:
¾” Swagelok tube/fittings, flanged inlet/outlet
Design of 600 psi, ambient
304 s.s. frame to be mounted on the wall
Pressure guage with isolation seal and valve
1. Provide a hand sketch P&ID
2. Provide a hand sketch GA