glubad55
Mechanical
- Nov 8, 2012
- 5
Hi! I'm pretty familiar with MS Project's basic features (not so much with Actual Work, etc) and I am having trouble getting my tasks to obey their contraints.
The biggest problem is getting tasks with "As Soon As Possible" constraints to do a true finish-to-start.
-They have dependency links throughout. 1-2-3-4-5...
-The first task is a "Start No Earlier Than." All others are "As Soon As Possible."
-They're set as FS with no lag, but they still wait for up to a few months to start. I can drag tasks into their place on the Gantt chart, but I could do that better on paper than on MS Project.
I can't post a screenshot because my photo doesn't have a weblink, but I have all tasks set to 0% for this project. I'll start with that.
The biggest problem is getting tasks with "As Soon As Possible" constraints to do a true finish-to-start.
-They have dependency links throughout. 1-2-3-4-5...
-The first task is a "Start No Earlier Than." All others are "As Soon As Possible."
-They're set as FS with no lag, but they still wait for up to a few months to start. I can drag tasks into their place on the Gantt chart, but I could do that better on paper than on MS Project.
I can't post a screenshot because my photo doesn't have a weblink, but I have all tasks set to 0% for this project. I'll start with that.