Scipio
Mechanical
- Mar 11, 2003
- 229
I've got a project coming up involving a size-on-size tie in to a high pressure (ANSI 900# line class) natural gas pipeline. I'm looking at three or four ways of doing it, probably one of the cleanest would be hot-tapping - assuming I figure out a way to bring the operating pressure in the pipeline down during the actual tapping procedure. The biggest problem I have with hot tapping right now is the size-on-size (8" into 8" factor, and the fact a number of people who wouldn't have a problem tapping, say, a 4" leg into an 8" run, don't trust size-on-size. Just wondering if anyone out there has ever had a real problem doing this (assuming it's properly engineered in the first place) or if it's one of those "I know a guy who knew a guy" stories originating from an improperly engineered application.