raydefan
Civil/Environmental
- Dec 14, 2004
- 59
I am working on road rehab project where several ramps need to be replaced to conform to ADA standards. There are a few ramps where existing traffic signals would be within the side slope portion of the new ramp. I have seen traffic signal bases modified with ramps before.
(see attached picture -
I need a construction note telling the contractor how to do it. My guess that they would sawcut and remove the existing sidewalk (can they sawcut up against the traffic signal base plate?) and then fill in the void with some sort of mortar. Does this sound right?
(see attached picture -
I need a construction note telling the contractor how to do it. My guess that they would sawcut and remove the existing sidewalk (can they sawcut up against the traffic signal base plate?) and then fill in the void with some sort of mortar. Does this sound right?