jmf
Mechanical
- Apr 19, 2001
- 5
I'm a mechanical engineer building a 40' x 50' steel column storage shed on my property that will store a large RV, boat, tractor, and other heavy equipment.
The slab foundation is a 40' x 50' monolitic slab (5" thick in middle, 12" thick on edges). Used 6" x 6" - 6 gauge welded wire (which came in a 5' x 150' role) in middle (at least 6" overlap and wired together) supported by solid fire brick to a 3" height. The edges have 3 No.4 rebar in a ":." shape (looking on end). The column footers have four No.4 rebar crossed (and wired together) with four No.4. The column footer also has a 20' No.5 rebar bent in the middle (in a V shape) around each pair of column J bolts.
With the contractor checked the pad location with a lazer level, we discovered that the end of the 50' mark the slab needed to be raised 28" to be level. (Note: Eyeballing shallow slope hill is difficult.) I got a local dirt contractor (and neighbor) bring 12 loads of dirt to the sight. Unfortunately, it was 12 loads of red (Georgia) clay mixed with gumbo. So, I had the dirt contractor (and still a friend) move the clay away and haul-in 12 loads of sand (Note: I live on the Georgia coastal plain where sand and clay is plentiful, gravel does not exist nearby. I'm 15 miles from a town of 5000 folks and the ready-mix company.) The dirt contract packed the sand as it was spread with his D5 Cat. I then rented a 9000# impact strenght reversible vibratory pad compactor (the only one in the area), and compacted it the next day.
The concrete contractor (who's from the next county and is not my neighbor nor relative) compacted the trenched thickened edge with his 3000# strenght pad compactor, then placed the rebar and wire over a 6 mil black plastic sheet.
Yes, the termite control company sprayed the footers.
The weather in mid-June was predicted to be low 70s in the morning, then mid to upper 80s, partly cloudy, 90%+ RH, and 30% chance of late afternoon thundershowers. Because this weather pattern will likely exist until mid-October, I decide to pray and pour concrete. (I was unable to get the concrete poured in early spring and can't wait until until fall for better and less hot weather conditions.)
On Friday (3 days after the dirt was compacted), the pad was poured with 40 yards of 5000 psi concrete. Used 5000 psi, instead of the standard 3000 psi concrete for durability reasons. (E.g., Salt water from a boat bilge or water softner will mess-up 3000 psi concrete.)
The pour began at 7:00 AM and the concrete contractor completed finishing work by 11:00 AM. However, he had not yet cut the contraction joints (he highly recommended that the joints not be cut for another 4 to 16 hours.) He left the site (for another job) stating that he would be back at the end of the day or early morning to complete the contraction joint cuts. By Noon, I had sprayed a concrete curing compound on the slab. (There is no water supply or well on this 30 acre lot yet.) Temperature at Noon was probably in the mid 80s.
By 1:00 PM, I estimate that temperature had risen to the low to mid 90s.
At about 5:00 PM the slab experience about 1/2" of thunderstorm rain over a one hour period. The steam (or visible water vapor) that was evaporating from the slab was a mystical sight. After the rainfall, I noticed that the curing compound did not wash off the pad. There were no marks on the pad surface and it appeared to be in good shape. We may have had some additional light (less than 1/4" rainfall during the night.
The next morning came, but the contraction joints did not get cut until about 11:00 AM (Saturday). (The contractor did show to cut late the previous day due to thunderstorm activity and did another job first.)
Shortly after the contraction joints were cut, my wife (and then I) noticed hairline cracks in the concrete. The cracks had a mosaic or map-like appearance all over the slab. The crazy looking cracks appeared more numberous about 4 hours after the cuts and are about 1 to 3 feet apart.
Were the contraction joints cut too late?
Was this crazy pattern cracking due to the cold rainfall on the hot concrete surface?
Could the cracking become a structural concern?
Is the cracking only a visual appearance problem.
What should I tell my wife? (I was a genius before this.)
Thanks for your insightful information and suggestions.
The slab foundation is a 40' x 50' monolitic slab (5" thick in middle, 12" thick on edges). Used 6" x 6" - 6 gauge welded wire (which came in a 5' x 150' role) in middle (at least 6" overlap and wired together) supported by solid fire brick to a 3" height. The edges have 3 No.4 rebar in a ":." shape (looking on end). The column footers have four No.4 rebar crossed (and wired together) with four No.4. The column footer also has a 20' No.5 rebar bent in the middle (in a V shape) around each pair of column J bolts.
With the contractor checked the pad location with a lazer level, we discovered that the end of the 50' mark the slab needed to be raised 28" to be level. (Note: Eyeballing shallow slope hill is difficult.) I got a local dirt contractor (and neighbor) bring 12 loads of dirt to the sight. Unfortunately, it was 12 loads of red (Georgia) clay mixed with gumbo. So, I had the dirt contractor (and still a friend) move the clay away and haul-in 12 loads of sand (Note: I live on the Georgia coastal plain where sand and clay is plentiful, gravel does not exist nearby. I'm 15 miles from a town of 5000 folks and the ready-mix company.) The dirt contract packed the sand as it was spread with his D5 Cat. I then rented a 9000# impact strenght reversible vibratory pad compactor (the only one in the area), and compacted it the next day.
The concrete contractor (who's from the next county and is not my neighbor nor relative) compacted the trenched thickened edge with his 3000# strenght pad compactor, then placed the rebar and wire over a 6 mil black plastic sheet.
Yes, the termite control company sprayed the footers.
The weather in mid-June was predicted to be low 70s in the morning, then mid to upper 80s, partly cloudy, 90%+ RH, and 30% chance of late afternoon thundershowers. Because this weather pattern will likely exist until mid-October, I decide to pray and pour concrete. (I was unable to get the concrete poured in early spring and can't wait until until fall for better and less hot weather conditions.)
On Friday (3 days after the dirt was compacted), the pad was poured with 40 yards of 5000 psi concrete. Used 5000 psi, instead of the standard 3000 psi concrete for durability reasons. (E.g., Salt water from a boat bilge or water softner will mess-up 3000 psi concrete.)
The pour began at 7:00 AM and the concrete contractor completed finishing work by 11:00 AM. However, he had not yet cut the contraction joints (he highly recommended that the joints not be cut for another 4 to 16 hours.) He left the site (for another job) stating that he would be back at the end of the day or early morning to complete the contraction joint cuts. By Noon, I had sprayed a concrete curing compound on the slab. (There is no water supply or well on this 30 acre lot yet.) Temperature at Noon was probably in the mid 80s.
By 1:00 PM, I estimate that temperature had risen to the low to mid 90s.
At about 5:00 PM the slab experience about 1/2" of thunderstorm rain over a one hour period. The steam (or visible water vapor) that was evaporating from the slab was a mystical sight. After the rainfall, I noticed that the curing compound did not wash off the pad. There were no marks on the pad surface and it appeared to be in good shape. We may have had some additional light (less than 1/4" rainfall during the night.
The next morning came, but the contraction joints did not get cut until about 11:00 AM (Saturday). (The contractor did show to cut late the previous day due to thunderstorm activity and did another job first.)
Shortly after the contraction joints were cut, my wife (and then I) noticed hairline cracks in the concrete. The cracks had a mosaic or map-like appearance all over the slab. The crazy looking cracks appeared more numberous about 4 hours after the cuts and are about 1 to 3 feet apart.
Were the contraction joints cut too late?
Was this crazy pattern cracking due to the cold rainfall on the hot concrete surface?
Could the cracking become a structural concern?
Is the cracking only a visual appearance problem.
What should I tell my wife? (I was a genius before this.)
Thanks for your insightful information and suggestions.