GoodnightKiwi
Geotechnical
Hi all -
Long time listener, first time caller
I'm trying to find some advice / help / reference with respect to the attached problem, where the passive wedge asssociated with upper wall (Wall A) extends over the active wedge of the lower wall (Wall B). The design approach needs to be an Ultimate Limit State one. The uprights are timebr poles with the embedded portion encased in concrete. Upright spacing is at 1.2 metre centres.
Does anyone have any advice / reference sources etc etc
Do any of these options sound reasonable:
1. Designing Wall A as if wall B didn't exist (i.e. as a 4.8m high wall with 1 in 2.5 (v:h) toe slope. This would however require huge poles and big embedment depths
2. Look at what percentage of Pp is overlapping Pa and add this percentage of Pp into the loads applied to Wall B (say as a traffic load)
3. Treat the embedded portion of Wall A as a strip footing with applied load and look at how a Boussinesq type bulb would extend laterally from Wall A to Wall B, and add additional load to Wall B
Thanks in advance
Long time listener, first time caller
I'm trying to find some advice / help / reference with respect to the attached problem, where the passive wedge asssociated with upper wall (Wall A) extends over the active wedge of the lower wall (Wall B). The design approach needs to be an Ultimate Limit State one. The uprights are timebr poles with the embedded portion encased in concrete. Upright spacing is at 1.2 metre centres.
Does anyone have any advice / reference sources etc etc
Do any of these options sound reasonable:
1. Designing Wall A as if wall B didn't exist (i.e. as a 4.8m high wall with 1 in 2.5 (v:h) toe slope. This would however require huge poles and big embedment depths
2. Look at what percentage of Pp is overlapping Pa and add this percentage of Pp into the loads applied to Wall B (say as a traffic load)
3. Treat the embedded portion of Wall A as a strip footing with applied load and look at how a Boussinesq type bulb would extend laterally from Wall A to Wall B, and add additional load to Wall B
Thanks in advance