dsdt
Structural
- Jan 18, 2021
- 14
The existing service is about 4m under ground level while my the anchor is about 2.5m deep at the same location (free length zone). Is it this okay? (I know it is okay if the service is above the anchor with this much clearance but not sure about if it is under. I don’t see the difference but maybe I am wrong?)