ahgeo11
Materials
- Feb 21, 2024
- 4
I'm wondering if the sieve and hydrometer performed on the same sample should meet up smoothly when combined on a curve. Say my sieve ends at 0.075mm = 28.5% passing, but my hydrometer starts at 0.0505mm = 33.54% passing, that is quite a jump in the graph if they were combined. Am I missing something in my understanding that these should theoretically match up with a smooth curve? Or is the percent passing in the hydrometer referring to something different and they need to be corrected to line up.
Hope this makes sense, thank you.