mayur
Civil/Environmental
- Jun 2, 2001
- 4
Hi,
I have a question regarding the lifting of 220 tons railroad bridge (110' long , 21' wide)
Made of two main plate girders (9' high, with 40 mm flange thk, 20 mm web thik.)
Floor beams of 2' high, 21' long connected with main girders with 20 mm High strength bolts with 152mm 152 mm by 9.2 mm angles on both sides of floor beams with 50 mm clear distance from the edge of the angles to the bolt holes
There is stringers between two floor beams and it is also bolted connection.
NOW, I AM THINKING THAT WHETHER THIS WHOLE ASSEMBLY CAN BE LIFTED IN ONE PIECE WITH THE FLOOR BEAMS OR NOT.
I REALLY APPRECIATE YOUR REPLY.
Thanks,
Mayur
I have a question regarding the lifting of 220 tons railroad bridge (110' long , 21' wide)
Made of two main plate girders (9' high, with 40 mm flange thk, 20 mm web thik.)
Floor beams of 2' high, 21' long connected with main girders with 20 mm High strength bolts with 152mm 152 mm by 9.2 mm angles on both sides of floor beams with 50 mm clear distance from the edge of the angles to the bolt holes
There is stringers between two floor beams and it is also bolted connection.
NOW, I AM THINKING THAT WHETHER THIS WHOLE ASSEMBLY CAN BE LIFTED IN ONE PIECE WITH THE FLOOR BEAMS OR NOT.
I REALLY APPRECIATE YOUR REPLY.
Thanks,
Mayur