stevenal
Electrical
- Aug 20, 2001
- 3,789
An office building served three phase through a wye/wye service transformer has a standby generator and UPS system. When service is lost, the UPS keeps the critical loads up while the generator cranks and the transfer takes place. Over the weekend, a primary phase was lost. The UPS kept the critical loads up until the battery ran down, and the generator never started. The rumor is the generator control will only sense a full three phase outage. Obviously, the desired outcome would be for the generator control to be able to sense the loss of any single, two, or three phases, start the generator, and perform a three phase transfer. My question is: Are these controls generally configurable in this manner or would a replacement be required? I cannot be model specific at this point, so just looking for the "in general" sort of response. Thanks.