cad0211
Structural
- Mar 1, 2018
- 19
I am trying to run LPILE for some cored piers that are 3 diameters apart. Per the soils report they must be a minimum of 5 diameters apart in one direction (normal to the load) and 8 diameters apart (parallel to the load) or else I need to use a reduction factor which they gave me. How do you incorporate that into LPILE?