EBF
Structural
- Jun 2, 2003
- 62
Does the MSJC/ACI 530 code have time frame for dating submittals like ACI does? Our specs require submittal of unit strength test results and the contractor has submitted a report that is almost 10 years old. I can't find anything to help me push back on this. Anyone else have to deal with this?