A fabricator is trying to get me to accept shipping bent plate metal deck closure as field welded - is this typical? I've always had these shop welded but usually only small scale stuff. Only ever worked in industrial. so I'm sure what would be typical for say large concrete floors in commercial (this is still an industrial project, just with a lot of metal deck/concrete floor). Also, how is puddle welding the deck to the beams below normally handled? Just leaving top flange of beams uncoated? Will probably swap puddle welds for screws but just curious.