LCMKS
Structural
- Sep 11, 2007
- 5
I am designing the connection at the base of a metal stud pony wall. It is along stairs, 4' tall, 3.625" thick and i'm applying a 200# load horizontally to the top of the wall per UBC 97.
Problem: I am getting very large uplift forces on the SMS screws at the base and on the shot pins which anchor the bottom track to the concrete slab.
Question: Does anyone have a beefier connection detail for the base of the wall to teh slab? or different way of analyzing the metal stud pony wall system to get smaller uplift forces?
Thanks!
Problem: I am getting very large uplift forces on the SMS screws at the base and on the shot pins which anchor the bottom track to the concrete slab.
Question: Does anyone have a beefier connection detail for the base of the wall to teh slab? or different way of analyzing the metal stud pony wall system to get smaller uplift forces?
Thanks!