Labratt1
Structural
- Apr 1, 2010
- 3
I am the quality control manager for a producer and I have a question. More specs are asking for trial batch data lately and it seems to me to be redundant since the mixes I usually submit are standard mixes that have 30+ independent lab test results. Yet I have had engineers deny the mix till I can run a trial bath even though we run trial batches on all our mixes once a year in the winter. They say the trial batch has to be more recent. I was wondering what the purpose of running a trial batch for each and every project served? If anyone can answer this I would be most appreciative.