Good Day..
In wind farm power plant, at 33/132KV step up substation portion with short circuit level of 25ka the following MV cables (XLPE/AL-PE/MDPE) are there:
1- 33KV cables (1/phase)from wind turbine to 33kv switchgear incomer (length=1000mtr)
2- 33KV cables (3/phase)from 33KV swicthgear to step up 33/132KV power transformer (170mtr)
accordingly we have a confusion which sides of cable must be grounded (sending or receiving end) at both cases and based on which international standard.
Thanks in advance.
In wind farm power plant, at 33/132KV step up substation portion with short circuit level of 25ka the following MV cables (XLPE/AL-PE/MDPE) are there:
1- 33KV cables (1/phase)from wind turbine to 33kv switchgear incomer (length=1000mtr)
2- 33KV cables (3/phase)from 33KV swicthgear to step up 33/132KV power transformer (170mtr)
accordingly we have a confusion which sides of cable must be grounded (sending or receiving end) at both cases and based on which international standard.
Thanks in advance.