FernandoL
Industrial
- Jun 29, 2016
- 9
Due to my little knowledge and also based on the need to use ASME I and ASME B 31.1 for the construction of a boiler and its power piping, in which items of these codes are defined the correct time to apply the non-destructive tests. In other words, before or after post weld heat treatment?