Good evening sorry my english please.
I'am work in a project on shore and i have a problem with the field quality manager and NDT Manager.
We have performer hydrotest on 32 pipepline by 31.3 code.
In a battery limits we expected a welded(<) plate in a stub pipe (BW) welded on process pipe.
FQM & NDTM want execute a RT Test on whole BW but is a problem's with my progress and program.
I succeeded persuade their of execute a VT(preparation) before weld and VT after first sweep for pipe with Pressur Test <50 Bar and RT on pipe with Pressure Test >50 Bar.
but my leader don't is pleased.
Please help me..Know you a para. of all codes where to be written exs.
"NDT Type on temporary weld (unlist components or element of process pipe) for pressure Test are company's discretion" or similar?
Thank you!!
P.S.
how to be my English?
please, correct it.
I'am work in a project on shore and i have a problem with the field quality manager and NDT Manager.
We have performer hydrotest on 32 pipepline by 31.3 code.
In a battery limits we expected a welded(<) plate in a stub pipe (BW) welded on process pipe.
FQM & NDTM want execute a RT Test on whole BW but is a problem's with my progress and program.
I succeeded persuade their of execute a VT(preparation) before weld and VT after first sweep for pipe with Pressur Test <50 Bar and RT on pipe with Pressure Test >50 Bar.
but my leader don't is pleased.
Please help me..Know you a para. of all codes where to be written exs.
"NDT Type on temporary weld (unlist components or element of process pipe) for pressure Test are company's discretion" or similar?
Thank you!!
P.S.
how to be my English?
please, correct it.