babman
Mechanical
- Aug 14, 2017
- 4
First post on here, so be gentle with me!
Can't say enough good things about this forum - especially for a young engineer - it has given me lots of design pointers and guidance in some tricky situations.
I was wondering if I could gather some advice on placing a nozzle penetration through a 8" blind flange.
I have been given varying advice from other engineers in the office on a design and would like some other guidance.
I have a classic cylindrical pressure vessel, vertically mounted with 2:1 elliptical heads.
The design has been used for several years on a skid unit, but there is an issue with the demister pad installed internally in the upper section of the vessel.
Our warranty engineers have either had to cut the vessel to remove these pads or dissemble a lot pipework for access.
Essentially to cut a long story short, the plan is to change a 1 1/2" nozzle in the centre of the upper head, to a 8" nozzle to allow access for removing the pad.
So far, following Lloyds Register (marine contract) and ASME B16.5, I have replaced the 1 1/2" inch RFWN 300# flange, with a 8" equivalent, stuck on a blind counter flange and I'm now trying to put the 1 1/2 nozzle through the blind flange, to connect with the associated piping.
Just wondering if there is a section of either Lloyds or ASME I should be looking at for guidance on penetrating a blind flange with another nozzle/pipe. The pipework is SCH 80 wall thickness.
One engineer suggested treating the blind flange as another vessel wall thickness and simply doing an area of replacement calc and another disagrees entirely and suggests instead of the blind flange, do a flanged reducer.
The only problem is we are going from 8" down to 1 1/2" so I would think we would need 2 reducers to do this. Considering the height of the vessel is just over 2 m, this would mean the nozzle will be sitting way higher than it currently is. The PV is sitting on a skid to be fitted in a compressor room on a LPG carrier - so we have restricted height between decks.
Any help/guidance would be much appreciated!
Design Pressure 18 bar
Shell and Head thickness 9mm Carbon Steel
Design Temo -52/+60 degree C
Can't say enough good things about this forum - especially for a young engineer - it has given me lots of design pointers and guidance in some tricky situations.
I was wondering if I could gather some advice on placing a nozzle penetration through a 8" blind flange.
I have been given varying advice from other engineers in the office on a design and would like some other guidance.
I have a classic cylindrical pressure vessel, vertically mounted with 2:1 elliptical heads.
The design has been used for several years on a skid unit, but there is an issue with the demister pad installed internally in the upper section of the vessel.
Our warranty engineers have either had to cut the vessel to remove these pads or dissemble a lot pipework for access.
Essentially to cut a long story short, the plan is to change a 1 1/2" nozzle in the centre of the upper head, to a 8" nozzle to allow access for removing the pad.
So far, following Lloyds Register (marine contract) and ASME B16.5, I have replaced the 1 1/2" inch RFWN 300# flange, with a 8" equivalent, stuck on a blind counter flange and I'm now trying to put the 1 1/2 nozzle through the blind flange, to connect with the associated piping.
Just wondering if there is a section of either Lloyds or ASME I should be looking at for guidance on penetrating a blind flange with another nozzle/pipe. The pipework is SCH 80 wall thickness.
One engineer suggested treating the blind flange as another vessel wall thickness and simply doing an area of replacement calc and another disagrees entirely and suggests instead of the blind flange, do a flanged reducer.
The only problem is we are going from 8" down to 1 1/2" so I would think we would need 2 reducers to do this. Considering the height of the vessel is just over 2 m, this would mean the nozzle will be sitting way higher than it currently is. The PV is sitting on a skid to be fitted in a compressor room on a LPG carrier - so we have restricted height between decks.
Any help/guidance would be much appreciated!
Design Pressure 18 bar
Shell and Head thickness 9mm Carbon Steel
Design Temo -52/+60 degree C