WWSME
Civil/Environmental
- Jul 5, 2012
- 9
We have a piping situation that is not ideal, but can't be avoided. We have a tank with roughly 10 feet of liquid which can drain down to roughly 1 ft of liquid. A vertical pipe draws liquid out of this tank, up and over the wall of the tank and back down the other side to a self priming pump at the same level as the floor of the tank. The pipe that goes over the wall is roughly 1 ft above the 10 ft high level of the tank.
My question has to do with what static height to use in calculating the NPSHA. It seems to me that I have to consider two situations: The first would be the NPSH at startup to lift the liquid to the height of the over-the-wall pipe so basically suction lift is as though the pump was at the same elevation as the over-the-wall pipe. The other situation is the NPSH after the system is primed and running, so becoming a flooded suction system so that the static height is now the distance from the over-the-wall pipe to the pump centerline.
Am I correct?
My question has to do with what static height to use in calculating the NPSHA. It seems to me that I have to consider two situations: The first would be the NPSH at startup to lift the liquid to the height of the over-the-wall pipe so basically suction lift is as though the pump was at the same elevation as the over-the-wall pipe. The other situation is the NPSH after the system is primed and running, so becoming a flooded suction system so that the static height is now the distance from the over-the-wall pipe to the pump centerline.
Am I correct?