Follow along with the video below to see how to install our site as a web app on your home screen.
Note: This feature may not be available in some browsers.
On the way down, the wind turbine also struck an electronic billboard that has been the subject of lawsuits involving the billboard’s owner and the New York City Buildings Department, according to the station.
Coop City Times said:The wind turbine was erected between Dec. 11 and 13, but hasn’t been activated since it went up.
There is an ongoing effort to change the zoning for the property to disallow things like 60-foot illuminated signs and wind turbines but that change hasn’t been made as yet.
This lesson has been re-not-learnt many, many times.
[URL unfurl="true" said:https://www.nrel.gov/docs/fy10osti/47072.pdf[/URL]]
The mechanical components of the test turbine were installed during the week of March
17, 2008, and the inverter was installed during the week of May 5, 2008. The duration
test began on May 7, 2008 following inverter installation and commissioning. The
commissioning checklist from the installation can be found in Appendix B. The initial
duration test was conducted over a period of approximately four months from May 7,
2008 to September 13, 2008. The test did not meet the requirement in the standard for
at least 6 months of operation.
On September 13, 2008, the turbine experienced an inverter failure. This likely occurred
because the parameters in the inverter were set to optimize power performance. This
may have led to overheating of the electrical components and eventual failure, see
Figure 5. The turbine was subsequently inoperable until October 7, 2008 when the
inverter was replaced. The parameters in this inverter were set for normal power
production. Since an inverter failure is considered a major failure by the Standard, the
duration test was restarted on October 7, 2008.
On October 14, 2008, Mariah Power requested that the test team stop and/or lower the
turbine in winds above 40 mph (approximately 18 m/s) due to a potential problem with
the top shaft. NREL complied with this request, but determined that the turbine would not
be able to achieve the 90% required operational time fraction. As a result, the second
duration test was terminated on October 14, 2008. Because the turbine operated for only
one week between the test restart and termination, those results are not reported here.
Paul Gipe [URL unfurl="true" said:http://www.wind-works.org/cms/index.php?id=551[/URL]]
Mariah and its Windspire will go down in history as another novelty Vertical Axis Wind Turbine that was doomed from the start. Tall and slender, it was, if nothing else, distinctive. Unfortunately, a tall and slender wind turbine mounted on a short tower is still a wind turbine on a short tower. Architectural ornamentation alone is not enough of a market to support a wind turbine manufacturer as Mariah learned to its regret.